Proposed: 12/16/2018
Committee Approved: 12/30/2018
Board Approved: 1/7/2019
Effective: 1/10/2019
Issue:
It is currently unsafe to build a second level tunnel in Tunnels because there is no way to secure tunnel boards.
Rule change/clarification:
A third layer of bales may be used for the sole purpose of securing boards for a second layer tunnel. Proper, safe step downs must still be present for this optional layer.
A second layer tunnel shall add one additional point. (i.e. a two turn tunnel on the first level is 3 points, on the second level, it is worth 4 points)
There must be at least one tunnel scoring one point.